Central Pipeline
For this extensive project, VanCon installed 31,600 LF of 48 IN welded steel pipe, with pipeline excavation of 130,000 CY, pipeline embankment, and cutting roads. VanCon installed blow-off facilities, a Turnout Meter vault, cathodic protection facilities, SWPPP, and erosion control measures. Additional features were 11,000 LF of parkway trail and equestrian trail, a pedestrian bridge, and pipeline connections. VanCon installed 600 LF of 36 IN HDPE, and 900 LF of 6 IN HDPE. VanCon built a new fluoride injection building along with civil site improvements, a new Mainline Valve vault, a new Interconnection & Flow Control vault and miscellaneous segments of new welded steel pipeline and fittings varying from 14 to 24 IN. The project included six canal crossings, lining the canal with 200 LF of concrete lining, and  200,000 SF of road reconstruction on Jordan Narrows Road. 