11400 S. Sewer Outfall Phase II
Construction of a sewer outfall line from 11400 S. to 11800 S. on the following roads: Charter Point Way, Chapel Rim Way, 11625 S., and 2700 W., consisting of 42" PVC sewer main, 10-20' deep, CCTV inspection, traffic control on UDOT roadway, 84" manholes. The length of the pipeline was 4,550 LF. Job included a 60" jack and bore under Midas Creek. Included removal of existing 10" PVC sewer main and reconnecting 48 sewer lateral connections along the alignment. Bypass pumping greater than 2,500 GPM. A large diversion structure was constructed in the intersection of 11800 S. and 2700 W. with stainless steel sluice gates. 